MA37 Albury Wodonga Regional Hospital Project
最近のニュースレター
  • 19th 3月 2026, Daily Brief

    Fix & Form continued works to grid 3

    C&D continuing NDD along Telstra line- Borella Rd and continued works to NEB West and IPO, change of pedestrian access

    Creative
    IPO continued walls linings

    SJTA installing hold down bolts

    Maintain work zones,

    Steel and materials are to be removed from the North by the 20/03/26 to allow structural steel deliveries and crane set up.

    C&D removal of container next week.

    Bookings have changed you are able to select the truck to help understand what's required.

現場天気予報
現在の現場の天気

最終更新日時: 0:01
温度: 16C (アプリ 16C)
風速: 0KMH
最大風速: 0KMH @0:01
午前9時からの雨: 0.0mm
最低気温: 15C @22:28 2026/04/04
最高気温: 24C @15:20 2026/04/04
突風: 4KMH
最大突風: 4KMH @0:01


観察元 - Bureau of Meteorology
観察場所 - Albury, NEW SOUTH WALES
タイムゾーン - オーストラリア東部標準時
予測 - 日曜日, 5 4月

Partly cloudy.
: 13C マックス: 24C
降雨の可能性: 30%パーセント
予想降雨量: 0 に 1mm


予測の出典 - Bureau of Meteorology
予測場所 - Albury, NEW SOUTH WALES
タイムゾーン - オーストラリア東部標準時
明日 - 月曜日, 6 4月

Shower or two.
: 13C マックス: 26C
降雨の可能性: 60%パーセント
予想降雨量: 0 に 2mm


重要な現場書類
現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に初めてですか?

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始