MA37 Albury Wodonga Regional Hospital Project - Public Project Site
-
19th March 2026, Daily Brief
Fix & Form continued works to grid 3
C&D continuing NDD along Telstra line- Borella Rd and continued works to NEB West and IPO, change of pedestrian access
Creative
IPO continued walls linings
SJTA installing hold down bolts
Maintain work zones,
Steel and materials are to be removed from the North by the 20/03/26 to allow structural steel deliveries and crane set up.
C&D removal of container next week.
Bookings have changed you are able to select the truck to help understand what's required.
Current Site Weather
Last Updated at: 12:01 AM
Temperature: 60F / 16C (App 61F / 16C)
Wind Speed: 0MPH
Max. Wind: 0MPH @12:01 AM
Rain since 9AM: 0.0in
Min Temp: 59F / 15C @10:28 PM 2026-04-04
Max Temp: 76F / 24C @3:20 PM 2026-04-04
Gust: 2MPH
Max Gust: 2MPH @12:01 AM
Observation Location - Albury, NEW SOUTH WALES
Time Zone - Australian Eastern Standard Time
Forecast - Sunday, 5 April
Partly cloudy.
Min: 55F / 13C Max: 75F / 24C
Chance of Rain: 30%
Expected Rainfall: 0in
Forecast Location - Albury, NEW SOUTH WALES
Time Zone - Australian Eastern Standard Time
Tomorrow - Monday, 6 April
Shower or two.
Min: 55F / 13C Max: 79F / 26C
Chance of Rain: 60%
Expected Rainfall: 0 to 0.1in
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enrol online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enrol online at your convenience and save yourself time.